Day 40-41

{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622747768273/{/gallery}

11/23/2009-11/24/2009

  • sip installation
  • begin metal roofing installation, measuring and felt
  • begin sheathing first floor

Day 39

{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622723640605/{/gallery}

11/20/2009

  • position boom truck in preparation for sip installation
  • install 5 second floor fiberglass windows
  • shore up tarps to withstand rain/wind until sip installation

Day 37

{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622705199567/{/gallery}

11/17/2009

  • bolt framing to steel jib crane support column
  • window delivery
  • install staircase enclosure walls
  • begin framing deck post, beams and parapet
  • install 2" foam for insulated window/door headers

Day 38

{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622709118361/{/gallery}

11/18/2009

  • continue framing staircase enclosure and deck
  • site visit from sip installers
  • cut window openings, second floor west wall
  • squaring/truing of second floor in preparation for sip installation
  • remove and replacement of first floor bedroom windows
  • connect jib crane support column to foundation
  • complete insulated headers with plywood and fasteners

Day 36

{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622705199519/{/gallery}

11/16/2009

  • remove and replace sip support glulam beam for size correction
  • continue sheathing second floor
  • build and stage staircase walls in preparation for installation