Day 10
- Details
- Created on Sunday, 11 October 2009 02:49
- Last Updated on Saturday, 16 February 2013 05:34
- Written by bibo
- Hits: 966
{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622558680642/{/gallery}
10/09/2009
- organize recycling
- inspection of foundation wall (passed)
- pour concrete for foundation wall
- pick up new doors (front, side door, deck)
Day 9
- Details
- Created on Friday, 09 October 2009 13:12
- Last Updated on Saturday, 16 February 2013 05:34
- Written by Administrator
- Hits: 890
{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622548508506/{/gallery}
10/08/2009
- jib crane arrives
- transport jib crane to metal fabrication for construction of support post
- installation of form boards for companion foundation wall
Day 7
- Details
- Created on Friday, 09 October 2009 13:01
- Last Updated on Saturday, 16 February 2013 05:34
- Written by Administrator
- Hits: 914
{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622423989191/{/gallery}
10/06/2009
- footing re-bar inspection (passed)
- pour concrete footings
Day 8
- Details
- Created on Friday, 09 October 2009 13:05
- Last Updated on Saturday, 16 February 2013 05:34
- Written by Administrator
- Hits: 930
{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622548508492/{/gallery}
10/07/2009
- sorting debris for recycle: brick, metal, wood, earth, concrete
- excavate water meter and temporarily shutoff water supply at street
- relocate water shutoff to above new foundation wall
- relocate electrical outlets for new foundation wall construction
- setting re-bar for new companion foundation wall
Day 6
- Details
- Created on Sunday, 04 October 2009 16:52
- Last Updated on Saturday, 16 February 2013 05:34
- Written by bibo
- Hits: 470
{gallery}http://www.flickr.com/photos/doddletrunk/sets/72157622386366187/{/gallery}
10/03/2009
- stepped footing re-bar construction
- stack chimney brick for reuse, move broken brick for recycling
- continued removal of low-voltage wiring